Plastic Industry

Posted:  06 Apr 2010 17:20
We currently operate 24/5 with three shifts.  Due to capacity limitations and an increasing work load, we are considering hiring a 4th (or swing) shift and expanding to a 24/7 schedule.  Does anyone have any recommendations on how to best implement and organize this change?

Please email me at brwilson@montrosemolders.com

Many Thanks,

Brendan Wilson
Posted:  06 Apr 2010 18:11   Last Edited By: Troy Nix
Brendan, there was a nice discussion about going to full coverage several months ago on the MAPP forum.

Either do a Search on "Shifts" or copy and paste this URL into your browser if the link doesn't take you to the righ location.

http://www.mappinc.com/plastic-industry-forum ...

Let me know if you have any questions.

Troy Nix
Posted:  06 Apr 2010 18:50
Thanks Troy
Posted:  26 Apr 2010 18:03
We moved to a 4 shift operation over 10 years ago and it was one of the best moves we did. It helped reduce absenteeism and allowed us to maximize our capacity. Our 4 shift schedule is outlined below.

Su, Mo, Tu

Team A (7 am – 7 pm)

Team B (7 pm – 7 am)

We, Th, Fr

Team C (7 am – 7 pm)

Team D (7 pm – 7 am)

Every other Saturday Team A/Team B works. The other Saturday Team C/Team D works.

The key to a successful implementation from the traditional 3 shfit/5 day schedule was to take some time to explain reasons for the move and then allow everyone to vote on 1st, 2nd and 3rd choices. We only had a few people who had to take their 2nd choice and none for their 3rd choice.

Good Luck.

Best Regards,

Team 1 Plastics, Inc.
Craig Carrel
President